Wednesday, 5 February 2014

Slab pour finished

Height of the DEB is realistic now!

Garage on the lower left


Water tanks on the lower right


Front porch and agg line under the slab. Agg line is used to drain any water away that may build up friom the rear or underneath ( I suspect).

I will need to talk to the SS as where the agg line exits is where the stairs will go so not sure where/how it's drained from that point.



Slab pour today!

Met with our SS onsite today for a catch up and an opportunity for Q&A.

Saturday, 1 February 2014

Foam, form work and reo

We visited the site this week and noticed the plumbers were onsite to start the ground drainage work. 

Spoke to the SS on Friday afternoon and he said that the foam, reo and form work would be done on Saturday, additional drainage work early next week and they'll be ready to pour the slab on Wednesday. We are going to meet the SS on Wednesday and see the pour happen!





Drop edge beam





Drainage and form work starts

Drainage has been laid in the pad, laundry on the left and kitchen on the right in the distance