Saturday, 16 August 2014

Painters on site

Drove past the house today and there was a guy sanding the walls and ceilings, getting ready to paint I guess.

Friday, 15 August 2014

Last weeks progress

While we've not had a site visit in a week, seeing the variety of trades parked out the front we assume the follow has been done

- Kitchen in
- Doors and skirting on
- Looks to be locked up as there's a dead lock on the garage internal door and the front door is boarded up
- More facade painting


Friday, 1 August 2014

Alfresco, facade batterns and solar wiring


Battens have been placed too close to each other so you can't see the gap between